Airbus Stevenage, ITC
Witnessed testing and commissioning of the lightning protection system to the ITC building at Airbus Stevenage: visual inspection, continuity testing, fall of potential earth testing and certification to a ten ohm limit.
- Client
- M&E contractor on the Airbus Defence and Space campus
- Location
- Airbus Defence and Space, Stevenage, Hertfordshire
- Sector
- Aerospace and industrial
- Year
- Commissioning
10 ohms
Maximum combined resistance
30 m and 50 m
Fall of potential probes
1
Witness demonstration
The challenge
A new technical building on a secure aerospace campus with a commissioning regime run to the Atkins Volume 1 specification. The lightning protection system had to be demonstrated once, in front of the client's witnessing agent and subject matter experts, with absent parties bound by the witnessed results. That put the emphasis on getting the method right first time: isolating each earth, testing by the correct method for the ground conditions, and recording every reading on the inspection record and site plan.
What we did
- Wrote the integrated test and commissioning procedure to BS EN 62305-3 Section 7, covering prerequisites, design parameters, pre start checks, test procedures, interface, documentation, demonstration, instrumentation, staffing and permits.
- Inspected the whole system: a 25 x 3 mm bare aluminium air termination network with all roof plant, flues and ducts cross bonded; 25 x 3 mm PVC sheathed down conductors connected to the steel frame at high and low level; and a bare 25 x 3 mm copper earth termination network terminating on earth bars in inspection housings, with external joints silver brazed and Denso wrapped.
- Tested every earth by the fall of potential method in soft ground: earth isolated at the earth bar, current probe at about 50 m and potential probe at about 30 m, driven no more than 200 mm, with the potential probe moved 5 m each way and the three readings averaged. Where the ground was hard we used the dead or known earth method against an independent electrode.
- Continuity tested every conductor that could not be seen, with leads connected at low and high level, and calculated the combined resistance of the earth ring against the 10 ohm maximum in BS EN 62305-3.
- Pre witnessed the results before offering the system for formal witnessing, then completed the test sheets and certificate for the O&M manual and upload to the project document system.
Outcome
The system was inspected, tested and certificated with all earth readings recorded against the site plan and a combined resistance below 10 ohms.
Standards
- BS EN 62305-3 Section 7
- Atkins Volume 1 commissioning specification
- BS 7430
- Compliance
- Maintenance
Related projects
Testing and maintenance · 2026
Wembley High Technology College and East Lane Primary School
Annual test and inspection of the lightning protection systems on two school sites, seven structures and 38 earth electrodes, with one certificate per site and a defect flagged for remedial action.
- Structures tested
- 7
- Electrodes tested
- 38
- Result
- Pass, 1 Attention
Structures tested
Electrodes tested
Result
Read case study
Student accommodation · 2025 to 2026
Owlstone Croft, Cambridge
Design, supply, installation, testing and certification of six separate Class IV lightning protection systems to two accommodation blocks and four terraces, plus a UKPN substation earth.
- Structures protected
- 6
- Contract value
- £18,900
- Protection class
- IV
Structures protected
Contract value
Protection class
Read case study
Healthcare and extra care · Annual test 2024
Addenbrooke Extra Care, Gosport
Lightning protection to an extra care housing scheme using the metal roof as the air termination, 19 aluminium down conductors and 19 copper bonded earth rods, followed by annual testing.
- Down conductors
- 19
- Earth rods
- 19 x 2.4 m
- 2024 annual test
- Pass
Down conductors
Earth rods
2024 annual test
Read case study