FABIERBuilding Performance
← All projects

North Kent College, Dartford

Lightning protection to a new steel framed college building: frame bonded as the down conductor, 25 x 3 mm aluminium tape roof network and nine driven earth rods, delivered in four visits.

Client
Maybourne and Russell, for principal contractor Willmott Dixon
Location
Oakfield Lane, Dartford, Kent DA1
Sector
Education
Year
2021

9

Driven earth rods

4

Site visits

4 days

Estimated site time

A new further education building for North Kent College under Willmott Dixon. The design used the steel frame as the down conductor network with driven earth rods, which is efficient on materials but demands tight sequencing: the frame has to be bonded at low level before the ground floor is closed, at high level before the roof goes on, the roof network after the roofers have finished, and the earth rods just before the groundworks are finished and the scaffold comes down. Miss a window and the cost of a return visit or builder's work opening up lands on someone.

  • Planned the job as four short visits over the build programme: low level frame bonds, high level frame bonds, roof network after all other roof works, and earth rods before groundworks completion. Total estimated site time was four days.
  • Bonded the frame at 20 m centres around the perimeter by drilling 10 mm holes in the steelwork and fitting M10 bonding clamps with 25 x 3 mm aluminium tape tails, rolled up at high level for the roofers to leave out.
  • Installed the 25 x 3 mm PVC coated aluminium air termination network once the roof was clipped out and bonded plant, flues, handrails and aerials into it with M10 clamps.
  • Drove nine earth rods to an initial depth of 2.4 m with a 110 V percussion hammer, under a Willmott Dixon service avoidance plan: the main contractor CAT scanned and marked each rod position, witnessed the driving and photographed it for the record. Percussion tool use was logged to a 44 minute daily limit per operative for HAVS control.
  • Tested each electrode with a calibrated digital earth tester and connected the down conductor tails through test clamps.

A steel frame system with nine driven rods delivered on four visits to suit the programme, with the frame carrying the lightning current and no external down tapes on the finished elevations. The system was tested on completion.

  • BS EN 62305-3
  • BS EN 62561
  • BS 7430
  • Protection
  • Earthing

A higher standard for what comes next.